Richter expected to fully reopen July 20th
Starting today, June 20, Richter Street will be closed between Stockwell to Cawston Avenues to southbound traffic during the installation of a new watermain. A complete closure on Richter Street between Stockwell and Cawston Avenues will be in effect June 25 until project completion.
Construction hours are Monday to Friday, 7 a.m. to 5:30 p.m., although work may occur outside of regular construction hours (evenings and weekends), to minimize impacts on residents and limit the time of active construction in the area.
Richter Street from Bernard to Doyle Avenues will be re-opened Monday, June 25.
Utility and road surface improvements are anticipated for completion July 20, including paving on Richter Street between Cawston and Clement Avenues starting approximately July 9. When complete, improvements will include a new watermain between Cawston and Bernard Avenues, safety upgrades at the intersection of Doyle Avenue and Richter Street and road resurfacing of Richter Street between Clement and Bernard Avenues.